- If your project is for an existing building, submit a copy of the previous building plan review approval letter and certificate. It is prohibited to occupy a building for which plans have not been examined or approved.
- Fire Protection System plan reviews (fire alarm, fire suppression, hood suppressions, and fuel systems) will be submitted using the FC Application for Fire Protection Systems.
- All other plan reviews will be listed under Fire Plan Review by selecting the "Apply for Permits Online" button in the upper right-hand corner of this page.
- A plan review fee will be calculated and an invoice generated by a Permit Technician.
- The plans are reviewed by a Deputy Fire Marshal after receipt of the fee.
- The review is usually completed within a three-week time frame; however, additional information may be required.
- Once the review has been approved as submitted and/or modified, an approval letter and certificate will be issued.
- A copy of the certificate must be posted as required in 13 AAC 55.100(b).
- Once work has been completed on-site and ready to open to the public, contact a staff member at (907)861-8383 or Fire.Code@/MatSuGov.us to schedule a final inspection.
- If there are deficiencies noted at the inspection, a timeframe will be established for completion of corrections. Once any deficiencies have been corrected, a certificate of occupancy will be issued and the plan review will be closed.